June 29, 2026, 7:53 PM · Policy Impact Report · 12 min read
FERC Gave the Grid 60 Days to Stop the Data-Center Power Subsidy. Three Years of It Already Cleared.
On June 18, 2026, federal regulators ordered six grid operators to rewrite how data centers and other large new users connect to the grid and how their costs are shared, so those costs stop landing on everyone else's bills. Tracing each dollar back to the auction that set it shows the order is forward-only: it cannot touch the data-center costs already locked into the 2025/26, 2026/27, and 2027/28 bills, and the earliest delivery year a new rule could plausibly reshape is 2029/30.
By Cumulant Research
Hover or tap an underlined term to see its definition.

The quick version
- Via the show-cause route, FERC's June 18 order can remove zero dollars from the three delivery years already billed or contracted. It writes forward-only rules, and those years cleared at auctions in February 2023, July 2024, July 2025, and December 2025, where the filed-rate doctrine generally shields a cleared price from retroactive change. A separate legal track (see takeaway 6) is the live exception.
- The $329.17 per MW-day price reaching about 67 million people in June 2026 belongs to the 2026/27 delivery year. The widely quoted 63% / $9.3B data-center figure belongs to a different auction, 2025/26. Stapling the two together is the most common error in current coverage.
- These data-center 'shares' are modeled estimates from PJM's independent market monitor, not metered allocations, and the three headline percentages use three different denominators: 63% is data centers' share of the 2025/26 price increase, 82% is how much forecast data-center load raised the 2026/27 auction's total cost, and 40% is data centers' share of the 2027/28 auction's total cost. They are not a trend and should not be read as one.
- By the delivery-year calendar, the earliest year a new large-load rule could plausibly bind is 2029/30 (bills starting June 2029). Households and businesses pay the data-center share for at least three delivery years regardless of what the operators file within 60 days.
- Even total FERC success mostly changes who pays, not how much. The monitor's own counterfactual shows the 2026/27 capacity cost falling from about $16.1B to about $8.85B without new data-center load, a difference of roughly $7.3B, but a scarcity floor keeps prices elevated either way.
- The one path that could break this finding is a Section 206 repricing of an already-cleared auction, a separate question the D.C. Circuit reopened in January 2026 by sending a PJM case back to FERC. Watch that docket, not the 60-day clock.
Figure
From $28.92 to $333.44 in four auctions
PJM cleared capacity price by delivery year, against the roughly $325 administrative cap
The 2026/27 and 2027/28 auctions cleared at their administrative ceilings, which the Shapiro settlement set near $325/MW-day but which rose with cost inputs to $329.17 and $333.44, so the last two bars are pinned against a cap, not freely rising. The $175 floor and roughly $325 cap are systemwide reference values; some zones differ.
Source: PJM Base Residual Auction results (PJM Inside Lines and BRA reports); cap from the FERC-approved Shapiro settlement via Utility Dive · $/MW-day · 2024/25 to 2027/28 delivery years
Why it matters
More than 67 million PJM households and businesses are already paying a data-center-driven capacity surcharge that this headline-grabbing federal order cannot claw back, meaning relief is years away regardless of the 60-day deadline. The framing distinction between cost reallocation and cost reduction shapes how utilities, hyperscalers, and ratepayer advocates should value the action, and the parallel Section 206 litigation is the only real channel for recovering already-billed dollars. For investors, it clarifies that elevated PJM capacity prices are locked through 2027/28 and floored by generation scarcity, not easily unwound by regulation.
The news hook
On June 18, 2026, the Federal Energy Regulatory Commission (FERCFERCThe Federal Energy Regulatory Commission, the federal agency that regulates interstate electricity markets and approves the rules grid operators use to set prices.), the federal agency that polices interstate power markets, issued show-cause orders to all six regional grid operators, including PJM InterconnectionPJM InterconnectionThe largest U.S. regional power-grid operator, coordinating electricity for about 67 million people across 13 states and Washington, D.C., from the Mid-Atlantic into the Midwest., the system that keeps the lights on for more than 67 million people across 13 states and Washington, D.C., stretching from New Jersey to Illinois. The orders give the operators 60 days, until about August 17, to either defend their current rules or file new ones for how very large new electricity users, above all data centers, connect to the grid and how their costs are split among customers.
FERC framed the action as a push to speed the connection of large new loads. But a core piece of it is cost allocationcost allocationThe rules deciding which customers pay for which grid costs, the lever FERC's order actually pulls by aiming to shift more of the bill onto large new users.: writing rules so the households and businesses already on the grid do not end up paying for the upgrades needed to serve a new hyperscale data center. Consumer advocates have spent more than a year arguing that this is exactly what has been happening.
The error this article corrects
Most coverage has welded two facts together: the much-quoted claim that data centers drove 63% of a record price jump, and the record $329.17 per megawatt-day capacity price that started hitting bills this month. Those numbers come from two different auctions for two different delivery years. Pulling them apart is where this analysis starts.
One price, two questions
PJM runs a capacity marketcapacity marketA market where the grid pays power plants to promise they will be available on the hottest or coldest days, separate from paying them for the electricity they actually generate. Think of it as a retainer fee for standby capacity.: alongside paying power plants for the electricity they actually produce, it pays them a separate fee just to promise they will be available on the worst demand days of the year. Think of it as a retainer for standby power. The price of that retainer is set in a once-a-year auction called the Base Residual Auction, normally held about three years before the power is needed. Because the auction happens years ahead and locks in a fixed price, it is a forward auctionforward auctionAn auction held years before delivery that locks in a fixed price now for power supplied later, so the cost is contracted long before it appears on a bill.: the cost is contracted long before it ever shows up on a monthly bill.
That timing is the whole story. By the time a regulator acts, the auctions that set the next several years of bills have already cleared. So the question is not whether data centers are driving up capacity costs. The monitor's own numbers say they are. The question is narrower and more consequential: of the data-center costs already flowing into bills, how many can the June 18 order actually remove, and how many are locked?
Figure
From $28.92 to $333.44 in four auctions
PJM cleared capacity price by delivery year, against the roughly $325 administrative cap
The 2026/27 and 2027/28 auctions cleared at their administrative ceilings, which the Shapiro settlement set near $325/MW-day but which rose with cost inputs to $329.17 and $333.44, so the last two bars are pinned against a cap, not freely rising. The $175 floor and roughly $325 cap are systemwide reference values; some zones differ.
Source: PJM Base Residual Auction results (PJM Inside Lines and BRA reports); cap from the FERC-approved Shapiro settlement via Utility Dive · $/MW-day · 2024/25 to 2027/28 delivery years
Why the cost is already locked
A show-cause ordershow-cause orderA FERC directive telling a grid operator to either justify its current rules or propose new ones within a set deadline, here 60 days. It produces rules going forward, not refunds for the past. is a forward-looking instrument. It tells a grid operator to justify its existing rules or file new ones, and whatever rules result apply to future auctions. It does not order refunds for prices that have already cleared. That limit is reinforced by a legal principle called the filed-rate doctrinefiled-rate doctrineA legal principle that once a rate (here, an auction's cleared price) is on file and approved, it generally cannot be changed retroactively. It is why a cleared capacity price is hard to claw back.: once a rate is on file and approved by FERC, it generally cannot be changed after the fact. A cleared capacity price is, in effect, a filed rate, which is why clawing one back is so hard. The Third Circuit, a federal appeals court, applied that doctrine to block a retroactive change to a PJM auction rule.
Run the calendar forward and the consequence is stark. The 2025/26, 2026/27, and 2027/28 delivery years all cleared at auctions held between July 2024 and December 2025. Those prices are set. Through the show-cause route, the dollars the June 18 order can strip from them is zero.
Figure
What the June 18 order can remove from the three billed years
$0
Data-center capacity dollars the show-cause order can strip from the 2025/26, 2026/27, and 2027/28 bills
Via the show-cause route only: those three years cleared at fixed forward prices the filed-rate doctrine protects. A separate Section 206 repricing is the live exception (see the closing section).
Source: Filed-rate doctrine analysis; Third Circuit precedent; FERC June 18, 2026 show-cause orders
Tracing each dollar to its auction
The cleanest way to see this is a ledger. Each delivery yeardelivery yearThe 12-month period (June through May) for which a capacity auction's price applies. The 2026/27 delivery year runs June 2026 to May 2027. traces back to exactly one auction, on one date, at one cleared price. Once you line them up, the headline figures snap into place, and the famous 63% turns out to belong to the 2025/26 auction (which cleared at $269.92, a roughly nine-fold jump from $28.92 the year before), not to the $329.17 price that is making news now.
Figure
The delivery-year ledger: every dollar tied to one auction
Which year cleared when, at what price, and whether the June 18 order can reach it
| Delivery year | Auction held | Cleared $/MW-day | Data-center share * | Bills appear | Reachable by Jun 18 order? |
|---|---|---|---|---|---|
| 2024/25 | Feb 2023 | $28.92 | baseline | Jun 2024, May 2025 | No (past) |
| 2025/26 | Jul 2024 | $269.92 | 63% of the price increase / $9.3B | Jun 2025, May 2026 | No (locked) |
| 2026/27 | Jul 2025 | $329.17 | 82% cost increase / $7.3B | Jun 2026, May 2027 | No (locked) |
| 2027/28 | Dec 2025 | $333.44 | 40% of total cost / $6.5B | Jun 2027, May 2028 | No (locked) |
| 2028/29 | Mid 2026 | clearing now | not yet modeled | Jun 2028, May 2029 | Unlikely (clears first) |
| 2029/30 | ~2027 | not cleared | not yet modeled | Jun 2029 onward | Yes (earliest) |
Data-center share (*) figures are the monitor's modeled estimates and use different denominators by year: a share of the price increase (2025/26), the percent by which forecast data-center load raised total auction cost (2026/27), and a share of total auction cost (2027/28). They are not a single comparable series and should not be read as a trend.
Source: PJM BRA results and reports; Monitoring Analytics; IEEFA; Utility Dive; FERC
Three of these years are marked No: locked. The 2028/29 auction is clearing right around now, before any rule filed in August could be reviewed and made effective. The first year a new rule could plausibly touch is 2029/30, with bills starting in June 2029.
Three percentages, three different denominators
It is tempting to read the data-center shares as a falling trend: 63%, then 82%, then 40%. They are not a series. Each is the market monitor's modeled estimate, and each measures a different thing. The 63% is data centers' share of the price increase in the 2025/26 auction. The 82% is how much higher the 2026/27 auction's total cost was because forecast data-center load was included (the cost would have been about 82% lower without it). The 40% is data centers' share of the total cost of the 2027/28 auction. Different numerators, different denominators.
These are modeled estimates, not metered allocations. No meter splits a capacity bill into a 'data-center' half and a 'household' half.
Holding that distinction matters because it stops a reader from inferring a story the data does not tell, that the data-center share is shrinking, or growing, in a smooth line. What the numbers do agree on is direction: forecast data-center demand is the single biggest force pushing these auctions higher.
Reallocating who pays is not the same as lowering the bill
Suppose FERC's effort fully succeeds and future rules shift the data-center share of costs onto data centers. Would bills fall to where they were before the surge? Mostly no. The monitor built a counterfactualcounterfactualA modeled estimate of what would have happened under a different assumption, here, what capacity costs would be if new data-center demand were removed. It is a calculation, not a measured split. for the 2026/27 auction, a modeled estimate of what the cost would have been with the forecast new data-center load stripped out. Total procurement cost falls from about $16.1 billion to about $8.85 billion, a difference of roughly $7.3 billion. Real money. But $8.85 billion is still far above the pre-surge norm.
Figure
Removing new data-center load lowers the bill by about $7.3B, not to zero
2026/27 PJM capacity procurement cost, with and without forecast new data-center load (monitor's modeled counterfactual)
This is a modeled estimate, not a metered split. The roughly $7.3B gap is what the monitor attributes to forecast new data-center load (the inclusion of which raised total cost by 82.1%); the remaining roughly $8.85B reflects retirements and slow new supply, a scarcity floor that stays even without data centers.
Source: Monitoring Analytics, Analysis of the 2026/2027 RPM Base Residual Auction; via Utility Dive and IEEFA · $ billions · 2026/27 delivery year
The reason is supply, not just demand. Power plants are retiring faster than new ones connect, so capacity is scarce. Scarcity sets a high floor under the price no matter who is bidding. Cost allocation, the lever FERC is actually pulling, decides who pays the bill. It does much less to shrink the bill itself.
When could a new rule actually bite?
Lay the regulatory clock over the auction clock and the mismatch is obvious. Every auction that sets a currently billed year cleared to the left of the June 18 order. The order's own 60-day deadline lands in August 2026; even on an optimistic path, the rules that follow have to be drafted, reviewed, and approved before they govern an auction. By then the 2028/29 auction has cleared too. The first delivery year a new large-load rule could plausibly reshape is 2029/30.
Figure
The regulator arrived after the auction cleared
When each delivery year's price was fixed, and when a new FERC rule could first bind
Feb 2023
2024/25 price set: $28.92/MW-day
Pre-surge baseline; results announced Feb 27, 2023. Bills June 2024 to May 2025. Locked.
Jul 2024
2025/26 price set: $269.92/MW-day
The 9.3x jump. Bills June 2025 to May 2026. Locked.
Jul 2025
2026/27 price set: $329.17/MW-day
Cleared at the cap. First hits bills June 2026. Locked.
Dec 2025
2027/28 price set: $333.44/MW-day
Cleared at the cap. Bills June 2027 to May 2028. Locked.
Jun 2026
FERC show-cause orders issued
All six RTOs given 60 days; filings due about Aug 17, 2026. Forward-only rules.
Mid 2026
2028/29 price clears
Auction (scheduled around June 2026) clears before any new rule could be filed, reviewed, and made effective.
Jun 2029
2029/30 delivery begins
The earliest delivery year a new large-load rule could plausibly reshape.
Data-center share percentages are deliberately omitted here because their denominators differ by year; they live only in the ledger table, beside that caveat.
Source: PJM Base Residual Auction results and reports; FERC June 18, 2026 show-cause orders; Utility Dive · auction clear dates and the show-cause timeline · February 2023 auction through June 2029 delivery
So the honest answer to the headline promise is that households and businesses keep paying the data-center share for at least three delivery years, whatever the operators file in the next 60 days.
The one thing that could break this finding
There is a single path that could reach into an already-cleared auction, and it is not the show-cause order. Section 206 of the Federal Power Act lets FERC declare an existing rate unjust and unreasonable and replace it. Whether that power can reach a price that has already cleared is contested. In a January 13, 2026 decision involving PJM's 2024/25 auction re-run, the D.C. Circuit held that FERC had wrongly concluded a Third Circuit ruling foreclosed its Section 206 authority, and sent the question back to FERC to decide what relief, if any, that section allows.
What to watch
The 60-day show-cause clock cannot touch the locked years. A Section 206 repricing might. If you are tracking whether any of the already-billed data-center dollars can actually be recovered, watch the Section 206 docket on remand, not the August filing deadline.
That caveat aside, the central finding holds. The instrument that grabbed the headlines, the 60-day order, arrives after the costs it targets were already contracted. The subsidy, if that is the word for it, was locked in at auctions that closed months and years ago.
What to watch
- The Section 206 docket on remand from the D.C. Circuit's January 13, 2026 PJM decision, the only path that could reprice an already-cleared auction.
- The roughly August 17, 2026 RTO/ISO filings responding to the show-cause orders and how they treat large-load cost allocation.
- The 2028/29 Base Residual Auction clearing now, which will likely lock in before any new rule takes effect.
- Whether any new rule can be drafted, approved, and made effective in time to reshape the 2029/30 delivery year.
How we did this
- Mapped each PJM delivery year to its single Base Residual Auction, its clear date, and its cleared price using PJM's official auction reports and Inside Lines releases, then cross-checked prices against IEEFA, Utility Dive, and RTO Insider.
- Separated the three data-center 'share' figures (63%, 82%, 40%) by tracing each to its source statement in the Monitoring Analytics analyses and the reporting on them, and confirmed that each uses a different numerator and denominator, so they cannot be read as a single time series.
- Took the 2026/27 counterfactual ($16,124,370,889 with forecast data-center load versus $8,853,172,918 without, an 82.1% difference) directly from the Independent Market Monitor's Analysis of the 2026/2027 RPM Base Residual Auction, rounded to about $16.1B, $8.85B, and roughly $7.3B.
- Established the 'forward-only' reach of the June 18 order from FERC's own description of the Section 206 show-cause process and from law-firm analyses (McGuireWoods, White & Case, Bracewell, Duane Morris), and the retroactivity limit from the filed-rate doctrine and Third Circuit precedent.
- Confirmed the live exception from the D.C. Circuit's January 13, 2026 opinion and contemporaneous legal summaries, which hold that FERC must reconsider whether Section 206 permits relief on an already-cleared auction.
- Used a hyphen, not an em dash, throughout, and converted every relative date to an absolute one tied to the June 2026 reporting window.
What this cannot establish
- The data-center 'shares' (63%, 82%, 40%) and the $16.1B-versus-$8.85B counterfactual are the Independent Market Monitor's models, not metered measurements. They depend on demand forecasts that can change, and reasonable analysts could model them differently.
- The claim that the earliest reachable delivery year is 2029/30 is a calendar-based judgment about how fast new rules can be drafted, reviewed, and applied; an unusually fast rulemaking, or PJM voluntarily proposing changes under Section 205, could shift that timing.
- The legal conclusion that the show-cause route can recover zero already-billed dollars rests on the filed-rate doctrine and current precedent. The Section 206 question is unsettled on remand, and its outcome could change the answer.
- Administrative caps are reference values; actual binding ceilings ($329.17 and $333.44) rose with cost inputs above the roughly $325 Shapiro figure, and some PJM zones can differ from systemwide numbers.
- How a wholesale capacity cost translates into a household's monthly bill (the retail pass-through) varies widely by state and utility, so the grid-wide totals here are not a per-customer estimate.
This is AI-assisted analysis under stated assumptions; it is not investment advice or a price target. Figures are as of the publication date and trace to the cited sources; markets and disclosures change.
Sources
- 01FERC Launches Aggressive Targeted Action to Speed Large Load Integration, Federal Energy Regulatory CommissionPrimary
- 02FERC Issues Section 206 Show Cause Orders Directing All Six RTOs/ISOs to Justify or Reform Large Load Integration Rules, McGuireWoodsSecondary
- 036 takeaways from FERC's data center interconnection decision, Utility DiveSecondary
- 04PJM Auction Procures 134,311 MW of Generation Resources; Supply Responds to Price Signal (2026/27 BRA), PJM Inside LinesPrimary
- 052026/2027 Base Residual Auction Report (July 22, 2025), PJM InterconnectionData
- 06Projected data center growth spurs PJM capacity prices by factor of 10, IEEFASecondary
- 07PJM capacity prices hit record high as grid operator falls short of reliability target (2025/26), Utility DiveSecondary
- 08Data centers were 40% of PJM capacity costs in last auction: market monitor, Utility DiveSecondary
- 092027/2028 Base Residual Auction Report (December 17, 2025), PJM InterconnectionData
- 10PJM Auction Procures 134,479 MW of Generation Resources (Dec 17, 2025 release), PJM InterconnectionPrimary
- 11Analysis of the 2026/2027 RPM Base Residual Auction (counterfactual; $16.1B vs $8.85B, 82.1%), Monitoring Analytics (PJM Independent Market Monitor)Data
- 12FERC approves PJM capacity auction price cap, floor, Utility DiveSecondary
- 13Gov. Shapiro Legal Action Against PJM Saves Consumers Billions Across 13 States, Commonwealth of PennsylvaniaPrimary
- 14PJM Capacity Auction Procures Adequate Resources (2024/25 results, Feb 27, 2023), PJM InterconnectionPrimary
- 15PJM Capacity Prices Hit $329/MW-day Price Cap, RTO InsiderSecondary
- 16D.C. Circuit Confirms FERC's Section 206 Authority to Reprice PJM Capacity Auctions Despite Third Circuit Section 205 Ruling, Troutman Pepper Locke (Washington Energy Report)Secondary
- 17Opinion, No. 24-1353 (D.C. Cir. Jan. 13, 2026), PJM capacity auction Section 206 case, U.S. Court of Appeals for the D.C. CircuitPrimary
- 18Appeals court vacates FERC decision on PJM capacity results for Delmarva zone, Utility DiveSecondary
Related
Data Centers Drove PJM's Record Power Price. The Cost of Their Growth Is Spread Across Everyone's Peak, Not Billed to the Newcomers.
On 1 June 2026 PJM's record $329.17/MW-day capacity price began landing on bills in 13 states, and on 18 June the federal regulator ordered all six US grid operators to justify or rewrite their large-load rules by 17 August. Reading the rate mechanics shows the catch is not that data centers dodge the bill, running flat around the clock, they pay a large absolute share, but that the extra cost their growth created is socialized across all customers' peak demand rather than charged to the loads that triggered it, and a federal fix would still have to clear both a wholesale rule change and 13 state retail dockets to change who pays.

The grid added a record 58 gigawatts. The risk NERC just raised to its top alert tier can't be measured in gigawatts at all.
A record year for building power plants and a rare top-tier reliability alert landed two weeks apart, and the instinct is to net them out. Our analysis finds the two answer different questions, the new supply settles whether there is enough power, while the alert is about what happens in the split seconds after a fault, so they are orthogonal (at right angles: they do not trade off), and reading one as a cushion against the other turns a headline into a blind spot.

DOE Didn't Ban Your Appliances. It Raised the Bar for the Next Rule, by Two to Six Times
On July 2 the Department of Energy said it would 'permanently end' home-appliance efficiency mandates, but its proposal repeals no rule now in force. It rewrites the math for future rules, lifting the 'significant savings' floor from 0.3 to 2 quads. Correct for a change of energy units and for the fact that the test is an 'or,' and the real tightening is roughly two to six times, not a clean 6.7x, and it bites a specific middle band of products, not the whole program.

The biggest data-center campus ever planned just died. The pipeline didn't notice.
On July 2, QTS terminated the Prince William Digital Gateway, ending a three-year legal war over a 2,100-acre campus billed as the largest ever planned. A test of the regional supply pipeline finds the loss is too small to register: counties one ring out had already booked more megawatts than the Gateway planned, and Dominion Energy's order book has lately grown by roughly a Gateway per quarter.
